10m Solar Panel progression bug (Identical to a closed bug from another user)
Need More Information
I'm having the same bug reported by another user, with the same bug name. A contract on Palatine station requires a 10m solar panel that is supposedly unlocked on Vallis Reach, but despite being in the Colonized stage (I have done all contracts on Vallation and all unlock contracts on Palatine) the contract to unlock the 10m Solar Panel is unavailable.
Included save file on Vallis Reach
Files:
2.3 Survival.rar
Access denied
Access denied
Access denied
Access denied
Access denied
I have the same bug
Hello Elaisa,
Upon loading the Save you've provided, I can see the Solar Panel 10 m being available in the G-Screen and can be built.
Could you please confirm that this is the case for you?
Kind Regards,
Bartosz
Keen Software House
Hello Elaisa,
Upon loading the Save you've provided, I can see the Solar Panel 10 m being available in the G-Screen and can be built.
Could you please confirm that this is the case for you?
Kind Regards,
Bartosz
Keen Software House
On reflection it's likely that I overlooked the fact that I acquired the 10m solar panel previously because it wasn't listed as a reward in the contract system on accepting, and so I wasn't expecting any part unlocks on completing it. That seems to be the case for most of the contracts, as only some seem to indicate that they will unlock part blueprints when in actuality most if not all do. This inconsistency was confusing to me
On reflection it's likely that I overlooked the fact that I acquired the 10m solar panel previously because it wasn't listed as a reward in the contract system on accepting, and so I wasn't expecting any part unlocks on completing it. That seems to be the case for most of the contracts, as only some seem to indicate that they will unlock part blueprints when in actuality most if not all do. This inconsistency was confusing to me
Hello Elaisa,
Solar Panel 10 m visible as "Solar Panel (Large)" along with Wind Turbine are listed as Rewards for completing Engineering - Manufacturing Facility Contract at the Vallis Reach Station.
Could you please confirm that is the case for you after Vertical Slice 2.4 release (VS2.4 releases today at 5PM UTC)?
Kind Regards,
Bartosz
Keen Software House
Hello Elaisa,
Solar Panel 10 m visible as "Solar Panel (Large)" along with Wind Turbine are listed as Rewards for completing Engineering - Manufacturing Facility Contract at the Vallis Reach Station.
Could you please confirm that is the case for you after Vertical Slice 2.4 release (VS2.4 releases today at 5PM UTC)?
Kind Regards,
Bartosz
Keen Software House
Replies have been locked on this page!